Bluewater files for intervener status for Goshen Wind leave to Construct

Goshen transmission mapLakeshore Advance
The municipality will seek intervener status for Next Era’s leave to construct for the Goshen Wind Energy Centre. Since the municipality only had 10 days left to file for intervener status, Bluewater’s Chief Administrative Officer Steve McAuley, asked council how they wished to proceed with the leave to construct.

“We need to deal with this notice because they come fast and fierce. It’s the nature of the beast,” said McAuley at the meeting. McAuley suggested to council that they seek intervener status, so they can be informed of the comings and goings happening with the Ontario Energy Board and also ask for an oral hearing and to have their costs to be covered. The exact same thing council requested for Next Era’s previous leave to construct for the Bluewater Wind Energy Centre.

McAuley said that since the municipality had requested intervener status and an oral hearing with Next Era’s Bluewater Wind Energy Centre, council can expect similar results, including not being appointed costs and not receiving the oral hearing. Read article

Advertisements

Posted on June 13, 2013, in Bluewater Project, Lakeshore Advance, Next Era, Transmission. Bookmark the permalink. Leave a comment.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: